Supply means matching the packing list, mark drawing and pieces. Over-length members change transport and must be said before cutting. Stack by grid line so early pieces do not bury later ones.
A common order is columns, beams, braces, then purlins and cladding. Sequence changes need the site engineer. Gutters and window flashings follow details.

Drawing approval and foundation handover also hold the shop; do not ask fabrication days only.
No invented span or client is used. Attach a size list to inquire.
Tiankai Southeast fabricates marked members from approved drawings and supports erection by mark number. Sizes, loads and delivery follow the confirmed design file and contract; this page does not turn uncalculated tonnage, thickness or time into a promise.
Tiankai Southeast fabricates marked members from approved drawings and supports erection by mark number. Sizes, loads and delivery follow the confirmed design file and contract; this page does not turn uncalculated tonnage, thickness or time into a promise.
- Check packing list and marks
- Stack by grid line
- Flash from details