Industrial Workshop Steel Erection Notes

Industrial Workshop Steel Erection Notes

A typical shop sequence from laydown to a stable bay, without unpublished client names.

Workshops usually check foundations and bolts, then stack by mark. Columns and a stable bay come before the roof so members are not free-standing in the wind. Mirrored pieces need the suffix, not length only.

Roads, laydown and crane positions must exist first. If a piece is missing, stop that bay. Temporary guys follow the erection plan.

Industrial Workshop Steel Erection Notes

Clad after alignment. Bolt tightening and coating touch-up are common handover items; the contract list governs.

This is a method note, not a safety plan, and it invents no client or tonnage.

Tiankai Southeast fabricates marked members from approved drawings and supports erection by mark number. Sizes, loads and delivery follow the confirmed design file and contract; this page does not turn uncalculated tonnage, thickness or time into a promise.

Tiankai Southeast fabricates marked members from approved drawings and supports erection by mark number. Sizes, loads and delivery follow the confirmed design file and contract; this page does not turn uncalculated tonnage, thickness or time into a promise.

  • Check foundations before lifting
  • Stack by mark
  • Roof after a stable bay